A WIP (Work-in-Progress) report is a financial schedule that shows the status of every active construction project — comparing what you've earned (based on percentage of completion) to what you've billed. It reveals whether you're overbilled (billed more than earned) or underbilled (earned more than billed) on each job. Banks and bonding companies require WIP reports to assess your financial health and set bonding capacity. Salisbury Bookkeeping builds and maintains WIP schedules for contractors in the $500K–$10M range using QuickBooks Online and NAHB standards.
If you need bonding capacity, a line of credit, or just want to know if you're really making money — you need a WIP report.
WIP stands for Work-in-Progress. A WIP report (also called a WIP schedule) is a financial document that shows the real-time status of every active construction project. For each project, it calculates:
Contract amount — the total contract value including approved change orders.
Estimated total cost — what you expect to spend to complete the job.
Costs to date — what you've actually spent so far.
Percent complete — costs to date divided by estimated total cost.
Earned revenue — contract amount multiplied by percent complete.
Billed to date — what you've actually invoiced.
Over/under billing — the difference between earned revenue and billed to date.
Surety companies use your WIP schedule to determine how much additional work you can take on. They look at your total backlog, overbilling/underbilling position, and profit fade across active jobs. A clean WIP report can increase your bonding capacity. A missing or sloppy one limits it — or kills it entirely.
Banks that lend to contractors want to see WIP reports alongside your financial statements. It tells them whether your reported revenue is real (backed by actual field progress) or inflated (overbilled). A WIP report that shows consistent underbilling is actually a positive signal — it means you have earned revenue you haven't collected yet.
Without a WIP report, your income statement can be wildly misleading. A contractor who bills 80% of a $1M project but has only completed 50% of the work appears profitable — but $300K of that billed revenue hasn't been earned yet. The WIP report catches this.
"Our lender used to question every draw request. Now we submit bank-ready reports that get approved in days, not weeks."
Include the original contract amount, all approved change orders, and the current total contract value. Don't include unsigned change orders or proposals — only what's contractually agreed.
Use your original estimate plus any known cost changes. Update this estimate at least monthly. The accuracy of your WIP depends entirely on the accuracy of your cost estimates. If your estimates are stale, your WIP is fiction.
Divide actual costs to date by estimated total cost. A $200K job with $120K in costs to date is 60% complete. Some contractors use physical completion percentage instead of cost-based — either works, but be consistent and document your method.
Multiply contract amount by percent complete to get earned revenue. Compare to billed to date. If earned exceeds billed, you're underbilled. If billed exceeds earned, you're overbilled. Net the overbilled and underbilled amounts across all projects to get your total WIP position.
WIP reports are only useful if they're current. Update cost estimates, change order amounts, and billing totals monthly. Review the WIP in your monthly financial meeting. This is where you catch profit fade — when a project's estimated total cost creeps up and your margin shrinks.
Using stale cost estimates. If you haven't updated your estimated total cost since the bid, your percent complete is wrong and your WIP is useless.
Not including change orders. Approved change orders increase both your contract amount and your costs. Missing them distorts your WIP position.
Mixing cost-based and physical completion methods. Pick one method and use it consistently across all projects. Switching methods between projects makes the WIP schedule unreliable.
Not doing it at all. Many contractors wait until their CPA asks for a WIP at year-end. By then it's a backward-looking exercise. Monthly WIP reports are a forward-looking management tool — they show you which jobs are fading before the damage is done.
Salisbury Bookkeeping — Eagle Mountain, Utah · Serving contractors nationwide · Last updated: March 2026
A 30-minute assessment will show where your WIP stands — and whether your books are ready for bonding or financing conversations.
Or call/text: 385-374-9295
Salisbury Bookkeeping — Eagle Mountain, Utah · Serving contractors nationwide